APATINSKA PIVARA, APATIN (brewery)
InvestMENT-teCHNICAL doCumentATION OF BUILDING FOR INCORPORATION OF 8 CYLINDRic-CONICAL FERMENTERS
General projects AG, VK, E, T, TM, El
1995.
EQUIPMENT DISPOSITION ARRANGEMENT conducted IN PHASES FOR COOLING COMPRESSOR STATION
Project supplement TM
1995.
Technical pre-documentation for workmanship of high pressure vessel - fermenter
1996.
Project with piping installation for incorporation of new filtration equipment in new building
General project T, TM
1996.
Project of cooling the new fermenters (CcT) and yeast
General project TM
1997.
PREPARATION OF elaboratION ANALYSIS OF DEMOLITION PHASES OF EXISTING FERMENTATION CELLAR AND investMENT-teCHNICAL doCumentaTION FOR INCORPORATION OF LAGER AND PRESSURE TANKS
Elaboration analysis AG, VK, TM, T, E, El
1997.
CO2 STATION
Project of existing situation
1997.
expert documentation supervision on project for brewhouse extension
1997.
Investment-technical documentation for extension of cooling system source
General project G, TM, E
1998.
Investment-technical documentation of new building for incorporation of 3 cylindric-conical fermenters
General projects AG, VK, TM, T, RIPK, E
1998.
Investment-technical documentation for reconstruction of existing fermenter building and replacement of existing fermenters with new ones
General projects RIPK, AG, T, TM, VK, E
1999.
Investment-technical documentation for incorporation of filling line to fill beer in casks, into existing adapted building
General project T
1999.
Technologic-mechanical project of connecting new pressure tanks with filling lines to fill beer in bottles, cans and casks
General project T
1999.
InvestMENT-teChniCaL doCumentaTION FOR INCORPORATION OF BEER FILLING LINE INto A NEW BUILDING
General project AG, TM, VK, E, T
2001.
preparation of project for reconstruction of steam boiler foundation
2001.
preparation of investment-technical documentation for products storehouse in kula
General projects AG, VK, T, TM, E
2001.
Investment-technical documentation for new barley and malt intake building
General projects AG, TM, E
2002.
preparation of investment-technical documentation for products storehouse in mladenovac
General projects AG, VK, TM, E
2002.
preparation of investment-technical documentation for outbuilding the air-compressor room
General projects AG, E
2002.
preparation of investment-technical documentation for filling lines to fill beer in pet bottles
General projects AG, T
2002.
hops cooling plant
General projects TM, E
2003.
preparation of investment-technical documentation for products storehouse in Šabac
General projects AG, VK, TM, E, IR
2003.
beer filtration plant
General project T
2003.
Water treatment plant
Preliminary design AG
2003.
new brewhouse
Preliminary designs AG, VK
2003.
fermenting lager cellar, CcT
Preliminary designs AG, E
2003.
expert surveillance over the brewhouse and fermenting lager cellar building
2003/2004
outbuilding and extension of brewhouse capacity from 10 to 14 brews in 24h
General projects IP, AG, VK, E, TM, Np
2004.
fermenting lager cellar, CcT
General projects AG, VK, TM, E, Np
2004.
extension of NH3 evaporative condensers department
General projects TM, Np
2004.
Inspection of NH3 pressure vessels
General project RIPK
2004.
Reconstruction of cooling NH3 compressor station
General project TM
2004/2005
Elaboration analysis of demounting part of equipment and installation in compressor station
2005.
lactic acid plant
General projects AG, VK, E, TM, TN
2005.
reconstruction of cooling installation
Engineering
2005.
water treatment building
General projects AG, VK, T, TM, E, NP
2005.
Reconstruction of process waters piping
Projects El, Np
2005.
INTERIOR AND EXTERIOR NETWORK OF WATER FIRE EXTINGUISHING SYSTEMS
General projects VK
2005.
Elaboration analysis of waste water flows
2005.
surveillance over the execution of ventilation and heating in water treatment building
2005.
Ventilation of chemicals department in water treatment building
Engineering
2006.
Reconstruction of receivers in NH3 system and evaporative condenser demounting
2006.
BANJALUČKA PIVARA, BANJA LUKA (brewery)
extension of brewery capacity to 1000000 hl of commercial beer per year
preparation of feasibility study with following documentation - preliminary design for providing resources according to international bank methodology
Preliminary designs T, AG, TM, VK, E
1998.
Investment-technical documentation of part of works and surveillance over the work execution of the buildings:
- new and reconstruction of existing cylindric-conical tanks
- yeast station
- CO2 recuperation station
- water treatment
- reconstruction of cooling NH3 compressor station
General projects T, TM
2002/2003.
CO2 Central distribution to consumers
General project TM, NP
Godina 2003.
bottle filling line
Preliminary design T
2003.
BEER FILLING LINE
General projects AG, VK, E, TM, T
2004.
surveillance over the beer filling line building
2004.
Beer filling line
Project of existing situation T
2004.
PIVARA "7. SEPTEMBAR" ZAJEČAR (brewery)
Investment-technical documentation for incorporation of beer filling line into an existing adapted bottle filling line building
General project AG, VK, TM, T
1997.
Investment-technical documentation for incorporation of equipment for filling line to fill beer in bottles and casks, equipment for juices preparation, equipment for intake, storing and distribution of concentrated cleaning agents into an existing adapted building
General project T, AG, VK, TM, E
1998/1999.
Investment-technical documentation of new building for incorporation 6 cylindric-conical fermenters
General projects T, K, AG, VK, TM, E, RIPK
1998/1999.
Investment-technical documentation of new building for incorporation of brewhouse equipment that should increase from existing 6 to 9 brews in the first phase
General projects AG, T, TM, VK
2001.
pet bottles filling line
General projects AG, T, E, VG
2003.
JAGODINSKA PIVARA, JAGODINA (brewery)
program arrangement of ice-cream and fruit-mash plant
1995.
Investment-technical documentation for incorporation beer filling line into an existing adapted beer filling line building
General projects AG, VK, T, TM
1996.
bottle filling line
Projects of existing situation T, VK, TM, E
1998.
EXPERT ESTIMATION THE BREWERY'S CONDITION AND PRODUCTION POSSIBILITIES
2003.
VRŠAČKA PIVARA, VRŠAC (brewery)
technical certificate of pressure tanks and workmanship, delivery and mounting of inox equipment for beer and cip unit and workmanship of inox installation for ducting the beer from lager tanks over pressure tanks to unit for filling beer in glasses
Godina 1995.
InvestMENT-teChniCAL doCumentaTION FOR INCORPORATION of EQUIPMENT FOR FILLING lines to fill BEER AND JUICE IN CANS
General projects VK, TM, T
1996.
PIVARA "RADUN", RAVNO SELO (brewery)
Organisation and expert control of building process and mounting of technological and energetic equipment, with the bottle filling line start-up
General projects AG, VK, T, TM.
1995.
Program arrangement of new brewery plant and partial general projects for building execution
1999/2000.
Technical control of investment-technical documentation for malt silo building
2000.
"PIVARA GRUJIĆ", NOVI SAD (brewery)
Technologic-mechanical project
2000.
value estimation of basic means of part of technologic, mechanical equipment and installations
2005.
BIP, BEOGRAD (brewery)
EXPERT ESTIMATION THE BREWERY'S CONDITION AND PRODUCTION POSSIBILITIES
2003.
MINI PIVARA, TEMERIN (brewery)
value estimation of basic means of technologic and mechanical equipment and brewery works
1998.
MINI PIVARA "YUGEN-TTT", ŠABAC (brewery)
Investment-technical documentation for mini-brewery
General projects AG, VK, T, E
2000.
FABRIKA ULJA "VITAL", VRBAS (oil and edible fat industry)
Investment-technical documentation for water treatment building
General projects AG, T, E
1996.
Documentation of possibilities of thermic-energy savings in desodorisation
General project T
1997.
usage of nitrogen for oxidation prevention
Preliminary design T
1997.
Investment-technical documentation for icorporation equipment for usage of nitrogen for oxidation prevention
General projects G, M, T, E
1998.
usage of nitrogen for products inertisation prevention
General projects T, AG
2000.
constructor documentation of reservoir and installations for oxidation prevention with nitrogen
2000.
NIS - NAFTAGAS, NOVI SAD (mineral water and soft drinks)
preparation of investment-technical documentation for incorporation of FILLING LINE to fill mineral water AND SOFT DRINKS IN PET BOTTLES IN JAZAK
General project T
2001.
FABRIKA CEMENTA, BEOČIN (cement factory)
Investment-technical documentation for extension of administrative building
General projects E, TM, Np
1995.
PP "IMPEX", SREMSKA KAMENICA (yoghurt and ice-cream plant)
Thermical calculation, heating and cooling installation arrangement for yoghurt and ice-cream preparation
General project TM
1995.
INDUSTRIJA MESA "NEOPLANTA", NOVI SAD (meet industry)
Preliminary design of industrial waste water pre-treatment
Preliminary designs AG, TM, T, E
1996.
ALFA, RAKOVAC (diary plant)
Project documentation of heat exchangers for yoghurt line
1996.
SANHE YAN JIAO, P.R.CHINA (fruit juice industry)
- in cooperation with YUGOIMPORT-SDPR, Beograd and "DELIŠES", Vladičin Han - preparation of technical-technologic documentation for building the rich fresh fruits nectar factory and for production and racking of fruit juices in p.R. of china
General project T
1996.
ZAVOD ZA ONKOLOGIJU, SREMSKA KAMENICA (oncology institute)
engineering of installation for recircular cooling of water in system for crio-cooling of helium
1996.
MLEKARA SUBOTICA, SUBOTICA (milk industry)
expert analysis of project documentation and validity of executed cooling plant building with proposition to remove its disadvantages
1997.
MINI SIRARSKA MLEKARA, KOVIN (dairy plant)
Technical control of general tehnologic-mechanical project
1998.
MLEKARA, BELEGIŠ (dairy plant)
Technical control of general T, TM, AG, VK, E projects
1998.
MLEKARA, BERANE (milk industry)
Investment documentation for milk factory
General project T
1999.
MINI MLEKARA, MOKRIN (dairy plant)
general technologic-mechanical project on the mini milk plant
General projects T, G, E
2000.
ZANATSKA MLEKARA, SELO DVORIŠTE - GOLUBAC (dairy plant)
Project documentation of dairy plant
General project T
2000.
KONTINENTAL MLEKARA, PETROVARADIN (milk plant)
Investment-technical documentation of milk plant
General projects AG, VK, T, TM, E
2000.
PROIZVODNJA BEZALKOHOLNIH PIĆA, KULPIN (soft drinks plant)
Revision of general techonologic-mechanical project
2001.
D.O.O. "PTI" - PROCESNO TEHNOLOŠKI INŽENJERING, 21000 NOVI SAD, Bulevar oslobođenja 28 tel/fax: +381 (0)21 63 38 412,e-mail: ptins@EUnet.rs, ptins@InfoSky.net |